Need to design a concrete cover for a concrete methane spill containment pit (5'x25'x4'deep). It's sized for 3' of spilled methane with 1' extra to the bottom of any vents.
Is there an industry generated code for the possible explosion pressure? What about depth of concrete cover for fire protection of reinforcing steel? We would like to place vents along two sides to direct flames away from the storage tank and pumps. How big should the vents be?