Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Methods to mitigate expansion of pyritic shales below slabs

Status
Not open for further replies.

dschauble

Geotechnical
Nov 25, 2003
1
Project in construction where unforeseen pyritic shale has been encountered beneath a portion of the building. Impacted foundation and utility excavations are being treated with bitumastic seal prior to concrete/utility placement; however, in areas where the pyritic material is present at the building pad subgrade elevation, looking for alternatives. Is there a rule of thumb for minimum depth of remaval and replacement? Should forms which allow for expansion be utilized to "support" the slab-on-grade to allow for long-term potential expansion of the pyritic material? or is that an cost=prohibitive option. Thanks in advance for your assistance.

dschauble
AdvantageEngineers.com
 
Replies continue below

Recommended for you

Don't use lime or cement stabilization.

Not sure about undercut requirements.

f-d

¡papá gordo ain’t no madre flaca!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor