Settingsun
Structural
- Aug 25, 2013
- 1,513
Hi all,
A micropile contractor has proposed a test to determine the skin friction provided by a particular ground layer. They have installed a micropile as follows:
- 219mm (8.6") steel tube casing used to drill to 25m (80') depth.
- 40mm (1.6") threaded steel rod down the centre of the tube. All except the bottom 3m (10') is sheathed to debond from the grout.
- Grouted to top of casing with "good flow to displace soils".
- Casing withdrawn with grout topped up along the way except for very near the end of casing withdrawal.
- Grout to achieve 50MPa (7ksi) before test.
- Tension test to be done with the jack placed on ground directly above the pile (on steel plates). I understand it isn't bearing on the pile as the grout didn't go to surface.
There was no borehole at the test location but it is expected that the pile is in 15-18m (50'-60') of soft clay and loose sands, overlying 7-10m (23'-33') of medium-dense sand.
Because only the bottom 3m of the threaded rod is bonded to the grout, the contractor is saying that the test load achieved can be attributed entirely to the bottom 3m of medium-dense sand. This doesn't seem right to me. Since the grout installation is essentially the same over the full length, the top 22m should be equally bonded to the ground as the bottom 3m. Since the load will be applied to the base of the micropile by the steel rod, the grout column will be in compression and capable of transmitting load to the upper ground layers (in my current opinion).
Appreciate comments on this. If only the bottom 3m is contributing to geotechnical capacity, what is the reason/mechanism that prevents the upper layers contributing?
I understand that counting only a part of the micropile length (in the target resisting ground layer) is a common and conservative *design assumption* but from what I've read it's not a reflection of the actual action of a micropile.
Thanks in advance.
A micropile contractor has proposed a test to determine the skin friction provided by a particular ground layer. They have installed a micropile as follows:
- 219mm (8.6") steel tube casing used to drill to 25m (80') depth.
- 40mm (1.6") threaded steel rod down the centre of the tube. All except the bottom 3m (10') is sheathed to debond from the grout.
- Grouted to top of casing with "good flow to displace soils".
- Casing withdrawn with grout topped up along the way except for very near the end of casing withdrawal.
- Grout to achieve 50MPa (7ksi) before test.
- Tension test to be done with the jack placed on ground directly above the pile (on steel plates). I understand it isn't bearing on the pile as the grout didn't go to surface.
There was no borehole at the test location but it is expected that the pile is in 15-18m (50'-60') of soft clay and loose sands, overlying 7-10m (23'-33') of medium-dense sand.
Because only the bottom 3m of the threaded rod is bonded to the grout, the contractor is saying that the test load achieved can be attributed entirely to the bottom 3m of medium-dense sand. This doesn't seem right to me. Since the grout installation is essentially the same over the full length, the top 22m should be equally bonded to the ground as the bottom 3m. Since the load will be applied to the base of the micropile by the steel rod, the grout column will be in compression and capable of transmitting load to the upper ground layers (in my current opinion).
Appreciate comments on this. If only the bottom 3m is contributing to geotechnical capacity, what is the reason/mechanism that prevents the upper layers contributing?
I understand that counting only a part of the micropile length (in the target resisting ground layer) is a common and conservative *design assumption* but from what I've read it's not a reflection of the actual action of a micropile.
Thanks in advance.