Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Microsoft Project 2003 Changing durations from days to hours

Status
Not open for further replies.

Kemira1122

Mechanical
Jul 10, 2007
1
0
0
GB
I have started a plan using days as the measure of duration for each task but now wish to change them all to hours. I am able to change the unit of time for newly inputted tasks but can't change the existing tasks.
Can anyone help
 
Replies continue below

Recommended for you

Good question! Try this:

Click on >Tools, >Macro, >Macro's, then select >Format Duration. Click on Run. The dialog box will appear that says "Select the duration unit for all tasks". choose hours and click on OK.

That should do it!!

Hope this helps,
J Black
 
Status
Not open for further replies.
Back
Top