Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Microsoft Project Vs Others

Status
Not open for further replies.

blooda

Mechanical
Oct 24, 2001
15
0
0
EU
Is it your view that microsoft Prject is limited as PM software, is their better stuff out there???

Your Views Please

Lets get this forum debating!!!

RGDS

AB
 
Replies continue below

Recommended for you

I would prefer Primavera above Microsoft project if you have the option. Far better control and scheduling options.
Your question if you can use MSP depends on the type of project . MSP2000 can work fine if you don't want any complex histograms / s-curves or early and late start calculations on your network logic. MSP will give you basic options and has a major drawback that you can only make 1 relation between 2 activities. Therefore no combination of SS and FF activities are allowed (often used for longer / overlapping act.'s).
Maybe this helps you a bit in the choice.
 
U can use the others too, but no more than 1 relation between 2 activities.
So the relation between act.A en act.B can be either one of FS,SS,FF,or SF but not SS and FF.
In a true forward&backward network analysis to determine Early and Late dates this would result in open ends on the activity , if only SS ( open finish ) or only FF (open start) was used. The combination of SS and FF ( possible in P3) will prevent this.
 
I would have to agree with Hanp regarding Primavera as a project management tool (not just planning), except that the cost is so much greater.
You could also look at Suretrak, the 'baby' version of Primavera, which hasn't the same extensive learning curve and gives lots of the Primavera benefits at similar price to MS Project.
Regards,
Rentaplan
 
what about the compatibility between primavera and msoffice? is there any possibility to create any reports in word or excel docs?
 
Status
Not open for further replies.
Back
Top