Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Minimum vessel OD for the requirement of manway

Status
Not open for further replies.

engr2GW

Petroleum
Nov 7, 2010
307
Hello,

I have seen MANY ASME coded vessels (separators) in the oilfield upto and sometimes more than 48" without manway. I was recently told that manway is required above 36".
Any thoughts, advice, insight, or experience on this will help.
My applications does not need any cleanout for the most part, but I want to be able to do atleast the minimum required
Thanks in advance

ASME BPVC VIII-1 2017, page 55, number 2 and 3.

As much as possible, do it right the first time...
 
Replies continue below

Recommended for you

engr2GW said:
I was recently told that manway is required above 36".

Told by who? Required by who? Sometimes nozzle or body flanges can serve.

Regards,

Mike



The problem with sloppy work is that the supply FAR EXCEEDS the demand
 
Many company specs and designs may mandate this, but I don't think there is a particular code requirement.

It's up to you depending on entry requirements, cleaning, inspection / repair and how big your other nozzles are and what access they permit.

for a 48" vessel it had better be a pretty small "man"

Remember - More details = better answers
Also: If you get a response it's polite to respond to it.
 
See ASME VIII Div.1 (2019)UG-46 INSPECTION OPENINGS.

Regards

 
Remember, the intention of the ASME code is to allow access to the interior of the vessel for inspection...

It is NOT TO GET A MAN INSIDE OF THE VESSEL AT ALL COSTS

Inspection can be done through judicious placement of small "thief hatches", inspection hatches and additional flanges at large nozzles.

Expensive "full body flanges" are sometimes used ...


MJCronin
Sr. Process Engineer
 
ASME BPVC VIII-1 2017, page 55, number 2 and 3.

As much as possible, do it right the first time...
 
engr2GW
Please. Don't waste my time.
ASME 2017 is a old edit.

Regards
 
The OP is on the ASME-track. If this question would’ve been asked for EN 13445, then there is a code requirement for inspection openings, depending on the vessel size. This requirement is quite different from ASME.
But that’s a different cookie ha

Huub
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor