Hi, We are Designing & constructing Refinery in Abu Dhabi. As the shell course were erected in last year December now when we are placing platform / pipe stiffener, the vertical weld clearance of 150 mm as API-650 is not achieving.
Can anyone pls tell me the as how to rectify this.
PS :- Removing the stiffener or moving the shell is not possible now.
Also pls advice if any other standard can be followed.
Can anyone pls tell me the as how to rectify this.
PS :- Removing the stiffener or moving the shell is not possible now.
Also pls advice if any other standard can be followed.