Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

mixed seismic site class

Status
Not open for further replies.

nbr1

Geotechnical
Feb 29, 2008
95
Does anyone have any experience with sites which are justified with the assignement of several site class designations....(A through F as noted in IBC Table 1613.5.2). Say you have a site with N-values or other that would support both a Site Class C and a Site Class D.

Specifically, I am interested to know if it is justifiable to average the Fa and Fv values from each site class; and use this average result as the basis for determining SDs and SD1.

Intuitively, I would think taking the most conservative site class designation would be okay; however, I would think it would also be more costly in all situations.
 
Replies continue below

Recommended for you

ASCE 7-05, Chapter 20 does not address the condition where you may two 'justifiable' site class conditions under one building area.

I was curious if adjusting/averaging the Fa and Fv values for the two site class conditions that were ascertained was justifiable.

Say for example you had very shallow rock under 1/2 of the building, then deep under the remainder.
 
You need to use the more conservative values. I would not use an average.
 