rconnor
Mechanical
- Sep 4, 2009
- 556
The firetubes on our boilers are corroding during wet lay ups and the problem has been tracked to a lack of mixing of the oxygen scavenging chemicals.
Currently, site is suppose to go down once a week, test the water and fire up the boiler for a little while to mix, if needed. However, this step gets skipped a lot and so there is insufficient mixing and the fire tubes corrode.
We are looking into placing a circulation line/pump off the blow down line that would circulate the water from the front blowdown drain and pump it back into the rear blowdown drain.
Are there other ways of mixing the chemicals and would this circulation line work? Also, since we are a hydroelectric company, electricity is virtually free while the natural gas isn't (hence why we want to move away from lighting the boiler to mix). Also, the solution would need to be simple from an operational stand point as these are auxiliary boilers and are low on the totem pole of things to get done during the day.
Any advice/input would be much appreciated.
Thanks
Currently, site is suppose to go down once a week, test the water and fire up the boiler for a little while to mix, if needed. However, this step gets skipped a lot and so there is insufficient mixing and the fire tubes corrode.
We are looking into placing a circulation line/pump off the blow down line that would circulate the water from the front blowdown drain and pump it back into the rear blowdown drain.
Are there other ways of mixing the chemicals and would this circulation line work? Also, since we are a hydroelectric company, electricity is virtually free while the natural gas isn't (hence why we want to move away from lighting the boiler to mix). Also, the solution would need to be simple from an operational stand point as these are auxiliary boilers and are low on the totem pole of things to get done during the day.
Any advice/input would be much appreciated.
Thanks