LincolnPE
Civil/Environmental
- Mar 12, 2011
- 203
TR-55 states that the composite CN value for disconnected impervious greater than 30% should be computed from Figure 2-3.
In the attached screen capture there is a 20ac site with 10ac unconnected pavement and 10ac pervious. HydroCAD is taking the weighted average to compute a composite CN of 69 instead of using Figure 2-3.
Is there a step I am missing?
In the attached screen capture there is a 20ac site with 10ac unconnected pavement and 10ac pervious. HydroCAD is taking the weighted average to compute a composite CN of 69 instead of using Figure 2-3.
Is there a step I am missing?