sakaran51
Electrical
- Mar 27, 2013
- 61
Hi,Everybody,
Here is an interesting situation,but real!
There are two steam turbine generators in two steel plants located two kilometers apart.Plant-A is existing. Plant-B under erection.
Plant-A -STG capacity 15MW 11KV- Type of boiler AFBC and WHRB-Connected to 132KV grid through a Generator Transformer.
Plant-B -STG capacity 8MW 11KV- Type of boiler only WHRB- No Grid.
The 11KV Switchboards of both the plants are tied together by means of overhead lines, with circuit breakers at both ends.The balance of power,if any,after steel plants consumption,will be exported to the grid through 132kV switchyard,which is available only in Plant-A.
There are four important likely scenarios out of many when the new plant becomes operational.
1.Both the generators operating in parallel with the grid.
2.Both the generators operating in parallel but in islanding.
3.Both the generators operating independently.
4.Either 15MW STG or 8MW STG only operating in parallel with the grid.
In order to meet the requirements of above conditions the following mode of operations are envisaged.
It is pertinent to note that the steam generation from WHRB boiler is very much variable unlike AFBC boiler and Plant B is having only WHRB.
1.Both the generators operating in parallel with the grid.
15MW STG-Set KW(Governor)/PF(AVR)
8MW STG-Set KW(Governor)/PF(AVR)
2.Both the generators operating in parallel but in islanding.
15MW STG-Set Frequency(Governor)/Voltage(AVR)-like swing machine.
8MW STG-Set KW(Governor)/PF(AVR)
3.Both the generators operating independently.
15MW STG-Set Frequency(Governor)/Voltage(AVR)
8MW STG-Set Frequency(Governor)/Voltage(AVR)
4.Either 15MW STG or 8MW STG only operating in parallel with the grid.
15MW/8MW STG-Set KW(Governor)/PF(AVR)-as applicable.
Hope the above settings are in order.Your views on this will be valuable.
Here is an interesting situation,but real!
There are two steam turbine generators in two steel plants located two kilometers apart.Plant-A is existing. Plant-B under erection.
Plant-A -STG capacity 15MW 11KV- Type of boiler AFBC and WHRB-Connected to 132KV grid through a Generator Transformer.
Plant-B -STG capacity 8MW 11KV- Type of boiler only WHRB- No Grid.
The 11KV Switchboards of both the plants are tied together by means of overhead lines, with circuit breakers at both ends.The balance of power,if any,after steel plants consumption,will be exported to the grid through 132kV switchyard,which is available only in Plant-A.
There are four important likely scenarios out of many when the new plant becomes operational.
1.Both the generators operating in parallel with the grid.
2.Both the generators operating in parallel but in islanding.
3.Both the generators operating independently.
4.Either 15MW STG or 8MW STG only operating in parallel with the grid.
In order to meet the requirements of above conditions the following mode of operations are envisaged.
It is pertinent to note that the steam generation from WHRB boiler is very much variable unlike AFBC boiler and Plant B is having only WHRB.
1.Both the generators operating in parallel with the grid.
15MW STG-Set KW(Governor)/PF(AVR)
8MW STG-Set KW(Governor)/PF(AVR)
2.Both the generators operating in parallel but in islanding.
15MW STG-Set Frequency(Governor)/Voltage(AVR)-like swing machine.
8MW STG-Set KW(Governor)/PF(AVR)
3.Both the generators operating independently.
15MW STG-Set Frequency(Governor)/Voltage(AVR)
8MW STG-Set Frequency(Governor)/Voltage(AVR)
4.Either 15MW STG or 8MW STG only operating in parallel with the grid.
15MW/8MW STG-Set KW(Governor)/PF(AVR)-as applicable.
Hope the above settings are in order.Your views on this will be valuable.