For example.....I have a 20 acre site and 10 acres flow to the detention pond. I have determined a pre-developed allowable runoff rate of 50 cfs. The detention pond is designed to release 30 cfs. How would you determine the runoff rate from the 10 acres that bypasses the detention pond? I used the modified rational method to model the detention pond.