I have a three span beam with two-three foot overhangs. I treated the ends with the overhangs as pinned and did one moment distribution using modified stiffness (0.75*stiffenss) at the pinned ends and one without modified stiffness. They both converge to within two decimal places (using Excel) but they got different answers at the interior supports. Is it proper to consider a continuous beam with an overhang to be a pinned end? Is modified stiffness mandatory for a pinned end? I thought it was just to speed up convergence which is not a problem with Excel anyway. Everything about the two spreadsheets is identical except the two stiffnesses.
Thanks,
DPA
Thanks,
DPA