dylansdad
Structural
- Nov 15, 2005
- 132
I have a 31,000 sf concrete slab placed mid September to mid October in 2021. I an unaware when the roof structure was installed and it was finally covered.
It is 8" thick slab underlain with 15 mil poly vapor barrier and 4" gravel.
It will receive a bead blast and an epoxy coating in an aircraft hangar facility.
The problem is the moisture (I guess Rh is the better word) levels are running anywhere from 89%-94% and the specifications require 72% for placement of the epoxy floor.
We are overall CM for the project and the subcontractor is of course saying we are "holding him up" by not allowing him to proceed with his covering.
I understand there are materials that can be applied to alleviate this problem, but we do not want to go this route ($) or sign any type of waiver/release for him to proceed.
We have been running the air conditioning at 72 degrees (we are in MS, high relative humidities here) for several weeks, but this has not helped.
Does this group have any other suggestions for "drying" this floor other than to wait it out?
Thanks in advance.
It is 8" thick slab underlain with 15 mil poly vapor barrier and 4" gravel.
It will receive a bead blast and an epoxy coating in an aircraft hangar facility.
The problem is the moisture (I guess Rh is the better word) levels are running anywhere from 89%-94% and the specifications require 72% for placement of the epoxy floor.
We are overall CM for the project and the subcontractor is of course saying we are "holding him up" by not allowing him to proceed with his covering.
I understand there are materials that can be applied to alleviate this problem, but we do not want to go this route ($) or sign any type of waiver/release for him to proceed.
We have been running the air conditioning at 72 degrees (we are in MS, high relative humidities here) for several weeks, but this has not helped.
Does this group have any other suggestions for "drying" this floor other than to wait it out?
Thanks in advance.