kaffy
Mechanical
- Jun 2, 2020
- 191
Good evening fellow engineers,
I am working on a project where I need to provide a 6' long beam with a capacity of 1 tonne (short load duration). As a beam trolley will be used on the beam, I will be following CMAA. The beam will be attached to ceiling(8in concrete) with post installed anchors. I will be doing the following checks
1: Beam size (Mono rail beam analysis)
2: Post installed anchors size (6 anchors, tension load on each anchor = 2800/6 = 466lb,I will use profis to determine the embedment depth, size and type) (2800 lb = capacity + approx weight of beam)
3: I will add the plates on ends to acts as a stopper
As it is overhead application and only anchors will be holding the beam and weight, I want to make sure I am not missing anything. Do I need to check anything else?
Thank You
Newbie
I am working on a project where I need to provide a 6' long beam with a capacity of 1 tonne (short load duration). As a beam trolley will be used on the beam, I will be following CMAA. The beam will be attached to ceiling(8in concrete) with post installed anchors. I will be doing the following checks
1: Beam size (Mono rail beam analysis)
2: Post installed anchors size (6 anchors, tension load on each anchor = 2800/6 = 466lb,I will use profis to determine the embedment depth, size and type) (2800 lb = capacity + approx weight of beam)
3: I will add the plates on ends to acts as a stopper
As it is overhead application and only anchors will be holding the beam and weight, I want to make sure I am not missing anything. Do I need to check anything else?
Thank You
Newbie