Buildwell
Structural
- Sep 1, 2021
- 10
Greetings all,
I have searched tirelessly for a methodology for producing a shallow sunken foundation for a small single storey structure. Frustratingly I have uncovered nothing other than an apparent dearth of information on the subject.
The proposed is a 4m x 6m reinforced slab of 150mm thickness and 225mm thick at the footing with an integral perimeter up-stand.
I have attached a section detail for clarity.
The problem I am having is that I want to avoid cold joints and place the concrete at once. The soil retaining up-stand is not tall but I am not confident that even with a relatively stiff 100mm slump, the concrete will not displace out into the slab pour if I attempt to cast both at once. Water ingress through any joints in the slab is not a concern as the foundation is fully protected by double layer 1200gm visqueen and EPS insulation. There will be 150mm clean gravel under the slab for drainage and thermal decoupling. Also, the water table in these parts is well below the point of concern. The soil is very heavy clay, and there are some small (non-threatening) trees within meters of the proposed structure, the 150mm reinforced slab thickness is merely a precautionary measure in case the trees and clay become troublesome in years to come.
Does anyone here have experience in such a task? Is a cold joint inevitable? Will I have to cast one element prior to the other? If so, which should be first? All rebar will be completed so sequential pours will be tied together regardless.
I thank you in advance for any light you can shine on this issue.
(I usually like a challenge but this one has got me on the ropes)
I have searched tirelessly for a methodology for producing a shallow sunken foundation for a small single storey structure. Frustratingly I have uncovered nothing other than an apparent dearth of information on the subject.
The proposed is a 4m x 6m reinforced slab of 150mm thickness and 225mm thick at the footing with an integral perimeter up-stand.
I have attached a section detail for clarity.
The problem I am having is that I want to avoid cold joints and place the concrete at once. The soil retaining up-stand is not tall but I am not confident that even with a relatively stiff 100mm slump, the concrete will not displace out into the slab pour if I attempt to cast both at once. Water ingress through any joints in the slab is not a concern as the foundation is fully protected by double layer 1200gm visqueen and EPS insulation. There will be 150mm clean gravel under the slab for drainage and thermal decoupling. Also, the water table in these parts is well below the point of concern. The soil is very heavy clay, and there are some small (non-threatening) trees within meters of the proposed structure, the 150mm reinforced slab thickness is merely a precautionary measure in case the trees and clay become troublesome in years to come.
Does anyone here have experience in such a task? Is a cold joint inevitable? Will I have to cast one element prior to the other? If so, which should be first? All rebar will be completed so sequential pours will be tied together regardless.
I thank you in advance for any light you can shine on this issue.
(I usually like a challenge but this one has got me on the ropes)