tvtran
Electrical
- Jan 6, 2015
- 2
HI, I AM LAYING OUT A GROUND SYSTEM FOR A METER PUMP STATION. I HAVE A GROUND RING SYSTEM FOR THE PCR, TRANSFORMER AND METER SKID. I ALSO HAVE SOME MOV'S (MOTOR OPERATED VALVES) LOCATED ALL AROUND THE STATION. THE MOV'S ARE 480V AND IS DRAWING 5 AMPS. THE MOV'S HAVE GROUNDING CONDUCTOR PROVIDED WITH THE MOTOR FEEDER 12/4 THHN THAT IS CONNECTED TO THE PANEL INSIDE THE PCR AND IS CONNECTED TO THE GROUND RING SYSTEM, DO I STILL HAVE TO CONNECT A GROUND FROM THE MOV HOUSING TO THE GROUND RING SYSTEM.