Hello I have a problem understanding how MS project calculates the duration from the start and finish dates.
for example i have a start date Wed 23/04 and a finish date Wed 30/4 which gives according to ms project 5 days..
To me it should 6 days.. what am I missing??
 
Replies continue below

Recommended for you

How many hours did you give the task? What time does it show the project starting and finishing?

TTFN

FAQ731-376
 
You are missing several steps:

Is this an assignment? What is the task type? When is the predessor task completing? If there is no assignment, look at the project calendar availability of working time, the options for calendar time and the ending time of the predessor task. That will let you know why it is taking longer than you expect.

Good luck
E. Lehnert, PMP - Certified MS Project instructor
 