Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

MS Project: how to use predecessor to start on earliest task?

Status
Not open for further replies.

annac

Computer
Jan 20, 2005
1
Does anyone know how to do the following in microsoft project? I would be very grateful for any ideas!

I have three tasks, Task 1, Task 2 and Task 3. I want Task 3 to start as soon as either Task 1 or Task 2 starts. How can I set this?

(E.g. if I use "1SS,2SS" as the predecessor, Task 3 only starts when the later of Tasks 1 and 2 starts, and not when the earlier one starts).
 
Replies continue below

Recommended for you

Status
Not open for further replies.

Part and Inventory Search

Sponsor