Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

MTBF of n redundant of N equipments

Status
Not open for further replies.

xj25

Electrical
May 7, 2011
110
0
0
ES
Hi,

I am looking for a closed formulae or method for getting the composed MTBF of m redundant equipments of N total.

I.e. 8 pumps, I need 6 working to do the job.
MTBF of 1 pump is X, What is the MTBF_6_of_8_pumps_working?

I got this formula from "introduction to reliability engineering" of E.E.Lewis, John Wiley & Sons but just for 1 of N redundant equipments:
MTBF= Sum_from_1_to_N[ (-1)^(n-1) * C_N_n / (n*Lambda) ]

where C_N_n is de binominal coeficient, Lambda the failure rate, and n the summing variable.

in the same book there is a discussion about m/N redundancy and it gets to a probability of failure (p.o.f.) method stimation,
i.e. for the pumps:
if 1 pump has p.o.f. of 1% so with this method I get 99.994% of probability of at least 6 pumps running

Where I am lost is in how to change from this p.o.f. values to MTBF (if it is possible using i.e. the MTBF of 1 pump)

Thanks for reading!
 
Replies continue below

Recommended for you

see:
MTBF and POF are not necessarily directly related. MTBF is a mathematical construct based on the exponential failure rate, and the failure rate does result in probability of failure, but requires knowledge of the time period over which that failure can occur. The POF of an exponential distribution decreases over time.

TTFN
faq731-376
7ofakss
 
I made this try, please comment if I am doing something stupid, lets do it with an example:

MTBF=1000h (lambda=0.001 failures/hour took as constant)
N=8 pumps total
m=6 pums at least to keep system running

First state: 8 pumps so MTBF_8= 1000/8= 125h for first failure (mean)
Second state: 7 pumps so MTBF_7= 1000/7= 142,85h for second failure (mean)
Third state: 6 pumps so MTBF_6= 1000/6= 166,66h for thir failure (mean)

With the third failure I have the real system fault so:
MTBF_at_least_6_of_8 = 125 + 142.85 + 166.66 = 434.5h (lambda=0.0023 failures/hour)

Regards!
 
I think that this particular form of calculation is more reasonable that those where the MTBFs are multiplied, so I agree with your calculation.

TTFN
faq731-376
7ofakss
 
Status
Not open for further replies.
Back
Top