Good Morning,
Are there any recommended opening / closing procedures for bringing a pump on line or closing one down by utilising the pump control calve located in the discharge pipe for each pump prior to joining the manifold?
We have 9 pumps, 7 of which are on line at any one time (2 dedicated standby units)
The pumps are all FIXED SPEED submersible canister type. (motor is with pump and not above floor level - the whole pump is lowered to the bottom of the 1100mm canister)
Diameter is 800mm and the manifold is 1400mm.
Fluid: Raw water
Would like to know if there are recommendations for the start-up procedures and any advice for correct installation considerations would be very much appreciated. Cavitation, surge, duration of closed head etc.
Best Regards
John
Are there any recommended opening / closing procedures for bringing a pump on line or closing one down by utilising the pump control calve located in the discharge pipe for each pump prior to joining the manifold?
We have 9 pumps, 7 of which are on line at any one time (2 dedicated standby units)
The pumps are all FIXED SPEED submersible canister type. (motor is with pump and not above floor level - the whole pump is lowered to the bottom of the 1100mm canister)
Diameter is 800mm and the manifold is 1400mm.
Fluid: Raw water
Would like to know if there are recommendations for the start-up procedures and any advice for correct installation considerations would be very much appreciated. Cavitation, surge, duration of closed head etc.
Best Regards
John