cuaslam
Mechanical
- Oct 7, 2012
- 1
I have set Start date for various tasks in a project with duration, and Finish date. Now some activities are delayed and could be started as per start date. I need to show the original start date, finish date and new start date and new finish date, all shown in the gantt chart.
Specific data is: Task Engineering Drawings Preparation, Start Oct 6, duration 10 days, Finish Oct 16, revised start date Oct 20 and revised Finish date Oct 30. Also need to mention % complete 30% on Oct 24.
I need steps to be followed for the data to be reflected in Gantt Chart.