JezNZ
Electrical
- Jun 17, 2021
- 73
Hi All,
Recently on an MV design-build project I had an unscheduled design review with the cable installing team after change of personnel.
For all our MV cable installs we calculate the minimum bend radii, maximum pulling tension, sidewall pressure, expected tensions and pressures etc. to ensure that the install will be to the manufacturer's requirements and best practice.
In a particular cable run (3C300AL PVC/MDPE Cu Wire Screen), the cable install team lead gave the feedback that they had concerns over multiple bends in a short section (approx 6 90 degree bends over 30 meters) that could lead to insulation kinking and premature failure, this being based upon collective years of install experience, despite compliance with the manufacturer's installation requirements.
Being unplanned, but not one to ignore practical experience, this feedback forced a post construction design change which was undesirable. So my question is, have people experienced this before, and is there any engineering method of calculation to account for this next time we perform such a design, or general rules of thumb to adhere to?
Thanks
Recently on an MV design-build project I had an unscheduled design review with the cable installing team after change of personnel.
For all our MV cable installs we calculate the minimum bend radii, maximum pulling tension, sidewall pressure, expected tensions and pressures etc. to ensure that the install will be to the manufacturer's requirements and best practice.
In a particular cable run (3C300AL PVC/MDPE Cu Wire Screen), the cable install team lead gave the feedback that they had concerns over multiple bends in a short section (approx 6 90 degree bends over 30 meters) that could lead to insulation kinking and premature failure, this being based upon collective years of install experience, despite compliance with the manufacturer's installation requirements.
Being unplanned, but not one to ignore practical experience, this feedback forced a post construction design change which was undesirable. So my question is, have people experienced this before, and is there any engineering method of calculation to account for this next time we perform such a design, or general rules of thumb to adhere to?
Thanks