Does anyone know the name of the CMU type that has a section of the block missing on one side to allow forming before pumping with grout? (unable to pump from the top.)

Thanks!
 
Replies continue below

Recommended for you

Half high on one of the long sides only.

Similar to a header block but with the short sides full height.

I'll see about posting a sketch.

Thank You.
 
Based on your description, it is a header block. a header block is half way high along one of the long sides and the webs are cut in half as well.

Let me know
 
Seems "Header Block" is a class of it's own, separate from the other styles of block, at least according to this site:


specpage20.gif




7.htm19.gif


Here are some additional images, none show a header block.



 
SteveBausch,

Please explain how you pasted the block pictures in your message - it is really COOL! (Cool: a word in use during the decade of the 1950's meaning neato, keen, crazy man, out-a-sight, its-the-bomb)
 
Wow! Images are what's been missing all along. I have ignored some postings because without a picture I was not sure what was being asked. You have broken new ground here.

Thanks,
Dave Adkins
 
Well, you know, we engineers cannot explain anything without sketching or drawing... LOL... otherwise we would have been reporters and or writers....

I think this picture/image posting is neat as well.... right on!
 