Normally it's usual to have 100% RX for underground piping systems containing oil products, 10% RX and 10% PT for aboveground piping systems. But what about firefighting, water and waste water piping systems? Any NDT requirement besides the normal visual inspection?
Also normally I see ITP's for this piping systems with 5 to 10% RX and PT. But there is any requirement on the codes? Mainly B31.3 or even NFPA.