Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Need Help Producing Maintenance Standards for Vacuum Interrupters

Status
Not open for further replies.

melissar

Electrical
Jun 10, 2003
1
Hi everyone!

I'm looking to upgrade some maintenance standards for vacuum interrupters. These are a fairly new product for my company and we don't have many standards in place.

I was wondering what kinds of tests were performed as part of preventative maintenance??

Thanks for your help!!
 
Replies continue below

Recommended for you

Maintenance test could be from visual, mechanical inspection and electrical test procedure that could be performed to the swgr and breaker with frequency that could varies from 1 year to 2 years as per testing practice recommended by the equipment manufacturer and testing organization such as NETA.

The highlight of the electrical test varies from resistance test, over potential across vacuum bottle, power factor or dissipation factor test on each pole and could be supplemented by infrared, ultrasound and other tests on the vacuum/swgr assembly.

SUGGESTION: Check with the equipment manufacturer, NETA and a local qualified testing company for advise in this matter.
 
Normally it is best to build from the manufacture's recommended testing methods and intervals. These should be viewed as the minimum standard. This information should be readily available in the instruction manuals furnished with the equipment.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor