selr
Structural
- May 20, 2005
- 1
hi, structural modifications have to be done to accomodate 3 new floors above an existing 5 storey building. I am unfamiliar with working with existing strucures and a few queries as to the best options of work method, replacement and connection etc. suitable for the situation.
-the placement of new pad footings 1.8x1.8.0.7 to new columns, founded 1.5m below ground slab level.
-some existing pad footings 2.4x2.4x0.9 founded at 1.5m have to take additional loads. Suitable increased bearing capacity is at a depth of 2.1m or increase in pad size to 3.6x3.6.
-how the columns can be connected to the underside of existing beams and if they should be reinforced concrete or composite. (the existing building is steel framed and encased in concrete for fire protection )
- How the exsiting columns can be best removed.
-the placement of new pad footings 1.8x1.8.0.7 to new columns, founded 1.5m below ground slab level.
-some existing pad footings 2.4x2.4x0.9 founded at 1.5m have to take additional loads. Suitable increased bearing capacity is at a depth of 2.1m or increase in pad size to 3.6x3.6.
-how the columns can be connected to the underside of existing beams and if they should be reinforced concrete or composite. (the existing building is steel framed and encased in concrete for fire protection )
- How the exsiting columns can be best removed.