mrnico
Structural
- Nov 30, 2006
- 8
We are putting up a 40x60 steel Mueller building on an existing outdoor slab 4"+ thick which was poured in the 1950s with no reinforcement. We are looking at doing a 24x24x24" footing at each of the six column feet with a rebar basket in it. The new slab will be 3000psi, 6" thick with #4 bars @16"o.c. each way. The loads I have are:
3x UPS 77"x38" @ 4990# each
12x batteries 74"x15.5" @ 3345# each
CLC Cabinet 77"x38" @ 4277#
transfer switch 36"x48" @ 1100#
These loads should be fine, but I wonder about the forklift wheels, 4"x6" contact patch each. Empty forklift weights 8000lbs and loaded weighs 12,000lbs. Sounds fine to me, but does anyone have any recommendations to back it up?
I am thinking that for the ramp going up is best to cut out the existing old 4" slab and pour in a thicker ramp up onto the new building with thickened edges and maybe more rebar in it, tied into the new 6" slab's steel. Thanks.
3x UPS 77"x38" @ 4990# each
12x batteries 74"x15.5" @ 3345# each
CLC Cabinet 77"x38" @ 4277#
transfer switch 36"x48" @ 1100#
These loads should be fine, but I wonder about the forklift wheels, 4"x6" contact patch each. Empty forklift weights 8000lbs and loaded weighs 12,000lbs. Sounds fine to me, but does anyone have any recommendations to back it up?
I am thinking that for the ramp going up is best to cut out the existing old 4" slab and pour in a thicker ramp up onto the new building with thickened edges and maybe more rebar in it, tied into the new 6" slab's steel. Thanks.