JimmyJunior
Electrical
- Jan 6, 2007
- 17
Recently our engineering group purchased and started installling 4 firepump assemblies in our utilities plant. Each of these assemblies consists of a firepump controller, a pump and a 250HP motor. The decision to replace the older firepumps was made because the older pumps were installed in 1962 and the pumps had started having problems. Each older pump was driven by a GE 250HP motor. In 2003 a new 2400kW (800kW ea standby) Kohler parallel, random access E/G system was installed. Prior to purchasing the E/G system
was modeled as were the 4 older firepumps using factory data (inertia, torque curves, etc). Static and dynamic motor starting was done under various operational scenarios using both the normal source and the E/G system. The modeling reavealed various problems that were corrected with the E/G manufacturer. The E/G system when finally installed and test ran all the commissioning tests without a hitch.
No such modeling and motor starting simulations were performed or allowed to be performed. The logic used was that as long as the motors were the same horsepower then everything would work as before.
Comments please.