Jmeng1026
Structural
- Jun 11, 2018
- 57
See the attached sketch. My client is removing the existing foundation wall and pouring a new wall. The contractor just proposed keeping the existing footing and slab and installing some compacted stone to match the top of slab height and then pouring a new footing on top of that.
Do you see any issues with this?
I have never seen it done but have also never been asked about it.
If it look acceptable should they install an 14" #4 bar vertically (4" into existing footing, 4" through slab and 6" into new footing)
Do you see any issues with this?
I have never seen it done but have also never been asked about it.
If it look acceptable should they install an 14" #4 bar vertically (4" into existing footing, 4" through slab and 6" into new footing)