Mechanical
- Sep 7, 2011
- 9
Hello,
Per NFPA 25 Table 13.1 Main Drain Tests are required Annually/ Quarterly.
We are trying to size the floor drain/sewer line to drain water from the Main Drain during the test.
The confusion is how much water flows from the 2" drain when its fully open. The city won't let the main drain to flow to the sidewalk.
Any insight on how the test is carried out if there is flooding issue during the test would be helpful.
Is it any good to size the floor drains/ sewer line for this particular test (taking in consideration the volume of water)? Also P-trap would slow down the flow.
Thanks !
Per NFPA 25 Table 13.1 Main Drain Tests are required Annually/ Quarterly.
We are trying to size the floor drain/sewer line to drain water from the Main Drain during the test.
The confusion is how much water flows from the 2" drain when its fully open. The city won't let the main drain to flow to the sidewalk.
Any insight on how the test is carried out if there is flooding issue during the test would be helpful.
Is it any good to size the floor drains/ sewer line for this particular test (taking in consideration the volume of water)? Also P-trap would slow down the flow.
Thanks !