gov spec requiring nitrogen purge while weld is being performed.gov spec ref's to ASME B31.1 and B31.9. Weld procedure QW-482 smaw, joint design vee,backing none,base metal (QW-403) P-# 1,,GRP # 1,Spec SA 106 GR-B,base metal .0625 to .436 all dia with in T range,,filler metals QW404,spec. no. SFA 5.1, AWS E6010 uphill& spec no 5.5 AWS E7018 uphill etc..???Why would nitrogen purge be used for this procedure ? Cannot find "code" ref that supports the use of nitrogen purge for these circustances. Reply to....