BONILL
Structural
- Mar 9, 2010
- 74
I'm designing a concrete slab over metal deck in which neither the steel beams nor the steel deck are composite with the slab (deck is used as a form). The total thickness of the slab is 6", (2" flute + 4" slab). The span is 8'-6" and the equipment load is 1.00 Ton/m^2. I am thinking of providing reinforcement in the flutes 3/4" clear from bottom parallel to the deck and temperature and shrinkage steel perpendicular to the deck at mid-depth. Thoughts are more than welcome.