333OnlyHalfEvil
Structural
- Mar 15, 2016
- 39
Hello everyone,
Quick question regarding framing for large steel buildings.
Do you typically use hot rolled steel for everything including floor joists? What are typical spacings? 4'-0" on center?
Or do you use hot rolled steel for just the big stuff (i.e. columns and beams) and then frame between with some other material (i.e. cold formed steel or wood)?
I'm more talking about the biggest buildings like skyscrapers and the like. I envision them being constructed as a giant concrete cantilever column with hot rolled steel girders framing out from it and then smaller hot rolled steel joists framing between the girders supporting metal decking below a concrete slab which serves as the floor. Does that sound correct? or wrong?
Thanks in advance
Quick question regarding framing for large steel buildings.
Do you typically use hot rolled steel for everything including floor joists? What are typical spacings? 4'-0" on center?
Or do you use hot rolled steel for just the big stuff (i.e. columns and beams) and then frame between with some other material (i.e. cold formed steel or wood)?
I'm more talking about the biggest buildings like skyscrapers and the like. I envision them being constructed as a giant concrete cantilever column with hot rolled steel girders framing out from it and then smaller hot rolled steel joists framing between the girders supporting metal decking below a concrete slab which serves as the floor. Does that sound correct? or wrong?
Thanks in advance