Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

NOT firm & unyielding Finish Base 1

Status
Not open for further replies.

Dirtcop24

Geotechnical
May 24, 2010
2
0
0
US
I'm currently on a project that has a subgrade issue that was not addressed and covered with Base. Six inches of Recycled Class II Base was moisture conditioned and compacted. The density results over the pumping areas were allegedly 95%+. However in my experience, it's sometimes possible to obtain passing tests and still have a pumping grade. I suggested that we proof roll it with a loaded water truck. And guess what, it was badly deflecting. This is to be an ally with heavy traffic. The structural section is six inches of Base and ten inches of 560C 3250 psi concrete (no steel). Should the concrete be placed over this pumping area without stabilizing it?? It should be noted, we are not pumping this concrete and loaded concrete trucks will be driving over this grade the day of the pour making it much worse. I suggested hogging out some of the base and increasing the concrete section to 12+ inches. Any thoughts would greatly be appreciated. Thank you
 
Replies continue below

Recommended for you

Dirtcop24 said:
1) Should the concrete be placed over this pumping area without stabilizing it??

2) This is to be an ally with heavy traffic. The structural section is six inches of base and ten inches of... concrete (no steel).
I suggested hogging out some of the base and increasing the concrete section to 12+ inches.

1) No.

2) Throwing (Owner's) money at the problem by increasing concrete thickness 2+ inches will solve nothing. If "time is of the essence", look into making the base much thicker than 6" (say, 18"+) and backfill with material suitable for wet conditions (crushed stone). This will still be expensive, but should solve the problem... when existing conditions are difficult, proper solutions are not "cheap".

 
Have you considered a grid in the subgrade? Pumping subgrades can be chased to great depth without finding stable conditions. A geogrid can help strengthen the upper layers to help bridge the soft areas.
 
Thanks for the quick responses. Geogrid was suggested at the beginning of the project. And unfortunately the Consultant dropped the ball and allowed the Base to be placed. I neglected to mention that the majority of the Finish Base is good. The pumping is isolated to an area 24'x 60' in a 3000' long area. Removing the Base and installing geogrid is the way to go. Obviously proceeding without addressing the deflecting area is never a viable option. And good point about throwing owners money at the problem! Thank you
 
Status
Not open for further replies.
Back
Top