Roadbridge
Civil/Environmental
- Apr 20, 2005
- 116
Several months’ back a small local contractor, who had taken over a contract through novation, approached me. He asked me would I be willing to run the contract as his site agent on a water supply contract, after careful consideration and study of the BoQ and specification of the original contractors tender I declined the position and advised the contractor not to sign the final novation contract, but to seek the contract under his own original tender rates.
This he did not do and went ahead and signed it. Last week I heard that he pulled his crew off the contract claiming that the local authority had not been fully forth coming in disclosing the extent of the amount of work that had to be made good such as testing of water mains and the relay off such.
The contractor further claimed that some of the major rates with in the bill were some uneconomical that the original contractor should not have been awarded the contract in the first place.
Has this contractor any redress in now breaking the contract and declaring it null and void or is his bound to honour it and lose his shirt in doing so?