Shokran
Mechanical
- Jun 18, 2014
- 1
Hi everyybody
I have a question regarding the calculation and effect of the nozzle piping load on vessel support, foundation and anchor bolt design specially on vertical vessel.
What is the common practice for large nozzle size 24" and 36" when the vessel weight is not high comparing to the nozzle load.
1- shall we consider separate load/moment in PV elite for each nozzle through "force/moment dialog" tab.
2- considering that, I will have 20 Number of M48 anchor bolts which seems too overdesign for a 8 ton vessel while without considering the load I will have 16 x M30.
3- Piping load is not final yet and I am using a standard SHELL DEP table, therefore I am not able to analyze which loads are canceled by each other.
Vessel size Dia x Tl/Tl: 2 x 5.1 m
Nozzle size: 24" and 36"
Vessel dead weight ~ 9 ton
I have a question regarding the calculation and effect of the nozzle piping load on vessel support, foundation and anchor bolt design specially on vertical vessel.
What is the common practice for large nozzle size 24" and 36" when the vessel weight is not high comparing to the nozzle load.
1- shall we consider separate load/moment in PV elite for each nozzle through "force/moment dialog" tab.
2- considering that, I will have 20 Number of M48 anchor bolts which seems too overdesign for a 8 ton vessel while without considering the load I will have 16 x M30.
3- Piping load is not final yet and I am using a standard SHELL DEP table, therefore I am not able to analyze which loads are canceled by each other.
Vessel size Dia x Tl/Tl: 2 x 5.1 m
Nozzle size: 24" and 36"
Vessel dead weight ~ 9 ton