pve5
Mechanical
- Sep 13, 2005
- 44
The vessel is in my case is spot radiographed, what is ASME code NDE requirement for nozzles located on circumferential weld joints.
Per UW-14 nozzle meeting the requirements of UG 36(C)(3), may be located on weld joints , provided the weld meets the requirements of UW 51 for the length equal to three times the diameter of opening on either side from centre line of nozzle.
Would above requirement, regarding full radiography of weld joints applicable to my case.
Thanks in advance
Per UW-14 nozzle meeting the requirements of UG 36(C)(3), may be located on weld joints , provided the weld meets the requirements of UW 51 for the length equal to three times the diameter of opening on either side from centre line of nozzle.
Would above requirement, regarding full radiography of weld joints applicable to my case.
Thanks in advance