stevenal
Electrical
- Aug 20, 2001
- 3,798
Seems like we've been getting more and more approval drawings from substation equipment vendors showing fuses in the neutral of the 120 V heating/lighting/receptacle circuits on these devices. We return marked up drawings with the neutral fuse removed. Is this just a case of international vendors being unfamiliar with USA single phase service? Or is this ever acceptable practice? Thanks.