Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

OEE - HOURLY CALCULATION

Status
Not open for further replies.

Rabdatorul

Mechanical
May 2, 2011
1
As we all know OEE is a multiplication of Availability, Performance and Quality.
There is some debate here on what formula it should be used to calculate OEE every hour. We are a one piece flow environment having the automotive industry as a customer.
Here are some of the formulas that our corporate office came up with:

OPTION 1:
The OEE by hour calculation should be:
The total number of good parts produced for that hour/the goal
of parts for that hour.
The goal is calculated using the available time we are running
during the hour/the Takt time.

OPTION 2:
The hourly OEE calc is:
Total assemblies produced - Rejects /Standard machine capability
for one hour

Also during a visit at the plant near our corporate office I saw OEE majority over 100% and I was very surprised knowing that 85% is considered "World Class"

What are your thoughts on this metters?

Your comments and help are highly appreciated.

Best regards,

Rabdatorul




 
Replies continue below

Recommended for you

Interesting.

Option 1 seems like it could be well over 100% depending on factors in the equation. When ever I see "goal" as part of a metric I get worried.
The "goal" of parts per hour varies? That just doesn't seem right.

I would say Option 2

what can you produce, how much is good, and how much could you produce if everything was "reasonably" perfect

my machine is capable of putting out 100 parts an hour
I make 98 but 1 is bad. I am at 97%


StrykerTECH Engineering Staff
Milwaukee, WI
 
Option 1 seems closer to the classic calculation.

Option 2 seems like it has the potential to hide issues with rejects by cranking out numbers.

I would stick to the classic calculation of OEE and give visibility to all three areas of importance

Quality % - Rejects
Availabity % - Machine/Production Uptime
Throughput % - Machine/Production Stability

I've seen 100% plus OEE at some manufacturing facilities. This could be a symptom of not setting appropriate standards to measure production.

Rich.....[viking2]

Richard Nornhold, PE
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor