SJBombero
Structural
- Dec 1, 2014
- 174
Does anyone have a detail showing what the typical solution is for a pier offset from the grade beam? I am designing a P&GB replacement for an existing spread footing. Since the structure (residential) is already there, I can't imagine that the drillers will be able to place the pier too close to the grade beam. The only thing that comes to mind is a haunch at the top of each pier that extends out to support the grade beam. Grade beam will be 8" x 16" and the piers at Ø16" or Ø18".