jjf1
Structural
- Jul 19, 2005
- 20
Maybe someone out there can help…………
We have a very large asphalt paved parking area installed circa 1935. It is surrounded on three sides with streams and creeks and is in an area with a high ground water table (+/- 4’ below grade)
The parking lot is well graded and rarely held any standing water.
Now, here’s the problem.
It was decided to replace the pavement, as the surface cracking and spalling was becoming a problem. When the first area was opened up, it was found that no sub grade preparation had been made and area was basically paved over (rock, clays & organics). It was decided to remove all the “soft stuff” and replace with “hard stuff”. Of course the contractor is claiming everything is “soft stuff” and he has to dig it all out (in some cases to 5’ deep) and of course the delays associated with all this work.
Our geotech support has been limited and we are addressing that problem.
Here is the direction we are headed…….please let me know your thoughts:
In the uncovered areas, fill and compact the areas to a depth of 12 below existing grade; place geotextile fabric; fill and compact with graded sand/stone to a depth of 5” below grade (7” of roadbed fill); top with 5” of coarse asphalt, bringing the area back to the original elevation.
Cap entire area (both opened area and existing pavement with geotextile fabric and then 3” of wearing surface asphalt (placed in 2, 1 ½” lifts)
Opinions, thoughts, suggestions appreciated.
jjf
We have a very large asphalt paved parking area installed circa 1935. It is surrounded on three sides with streams and creeks and is in an area with a high ground water table (+/- 4’ below grade)
The parking lot is well graded and rarely held any standing water.
Now, here’s the problem.
It was decided to replace the pavement, as the surface cracking and spalling was becoming a problem. When the first area was opened up, it was found that no sub grade preparation had been made and area was basically paved over (rock, clays & organics). It was decided to remove all the “soft stuff” and replace with “hard stuff”. Of course the contractor is claiming everything is “soft stuff” and he has to dig it all out (in some cases to 5’ deep) and of course the delays associated with all this work.
Our geotech support has been limited and we are addressing that problem.
Here is the direction we are headed…….please let me know your thoughts:
In the uncovered areas, fill and compact the areas to a depth of 12 below existing grade; place geotextile fabric; fill and compact with graded sand/stone to a depth of 5” below grade (7” of roadbed fill); top with 5” of coarse asphalt, bringing the area back to the original elevation.
Cap entire area (both opened area and existing pavement with geotextile fabric and then 3” of wearing surface asphalt (placed in 2, 1 ½” lifts)
Opinions, thoughts, suggestions appreciated.
jjf