sparkview
Electrical
- Nov 12, 2015
- 59
Hi all,
Our Powerplant is currently in the preliminary construction phase of a new Reciprocating Engine powerplant consisting of 6x17 MW engines.
This new powerplant totaling 102MW will be tied to our 60 kV system by three 50 MVA step-up transformers. The idea is currently to seek the possibility of integrating an On-Load Tap Changer (OLTC) into these new transformers. As I can understand the integration of OLTC controlled by an AVR can potentially have adverse interactions with the Generators AVR. All of the 6x17MW are supplying a 13.8 kV double bus system and then stepped-up by the three 50MVA transformers to the 60 kV double bus system upstream. As I can understand, the generator AVR and OLTC should operate in a carefully coordinated manner to avoid faster generator AVR and slower OLTC controls hunting each other.
I was wondering if anyone could share their opinion on this matter.
Jairo
Our Powerplant is currently in the preliminary construction phase of a new Reciprocating Engine powerplant consisting of 6x17 MW engines.
This new powerplant totaling 102MW will be tied to our 60 kV system by three 50 MVA step-up transformers. The idea is currently to seek the possibility of integrating an On-Load Tap Changer (OLTC) into these new transformers. As I can understand the integration of OLTC controlled by an AVR can potentially have adverse interactions with the Generators AVR. All of the 6x17MW are supplying a 13.8 kV double bus system and then stepped-up by the three 50MVA transformers to the 60 kV double bus system upstream. As I can understand, the generator AVR and OLTC should operate in a carefully coordinated manner to avoid faster generator AVR and slower OLTC controls hunting each other.
I was wondering if anyone could share their opinion on this matter.
Jairo