Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Overage length laydown and expansion loops

Status
Not open for further replies.

zoomi

Marine/Ocean
Aug 29, 2005
15
0
0
GB
I've been asked about a 2km long umbilical and what "overage" and the size of expansion loops at one end are required.

I heard that ordering 1% over the point to point length is appropriate and it's dependent on seabed topography.

What codes have anything on this? Is 1% too much?

Thanks
 
Replies continue below

Recommended for you

You can't just say 1% without due regard for the length alone not to mention topography and details of end connections too. Example 1% of 100 meters = 1 meter. Not going to be able to do much with that 1 meter length.

**********************
"Pumping accounts for 20% of the world’s energy used by electric motors and 25-50% of the total electrical energy usage in certain industrial facilities."-DOE statistic (Note: Make that 99% for pipeline companies)
 
Zoomi, the overlength required is the the pull in though the J-tube, you could get the actual lenght from the J-tube lenght + the lenght required for tie-in + the slack required for laydown. Your pipeline engineering performing the J-tube pull-in analysis could provide this.

Narendranath R
Pipeline engineering is made easy with state of the art computer software, visit
 
Status
Not open for further replies.
Back
Top