s0hxy
Mechanical
- Mar 13, 2008
- 14
I would like to start applying budgeted units to activities within my schedule. Scenario:
My schedule is based on 6 day/week @10hrs/day. Some resources are utilized on applicable activities for 10hrs/day.
In the case above: How do I do I load resources to the activities while taking in to account Reg. and Overtime Rates? Reg. Rate= 8hrs/day, OT Rate=2hrs
Keep in mind that I will have to insert actual mhrs/cost against this activity in the future
Any help on the setup of this would be great!
Thanks
My schedule is based on 6 day/week @10hrs/day. Some resources are utilized on applicable activities for 10hrs/day.
In the case above: How do I do I load resources to the activities while taking in to account Reg. and Overtime Rates? Reg. Rate= 8hrs/day, OT Rate=2hrs
Keep in mind that I will have to insert actual mhrs/cost against this activity in the future
Any help on the setup of this would be great!
Thanks