INSPECTACON
Materials
- Nov 9, 2014
- 7
I was wondering if some one could give me some reference with regards to why you would need to bring P15E (p91) material down to 200F prior to PWHT all I could find was that most shop purchased P91 filler has more nickel than does the parent metal which implies the weld must be cooled down to 200 F prior to PWHT ( in order to form 95% martensite prior to PWHT).The only exception may be welds thicker than 4" thk and true matching filler. The higher nickel filler is more ductile than matching filler and thus reduces the likelihood of cracking in the shop prior to PWHT due to handling stresses ( ie pushing the bundle into the oven). If we are welding in the shop 8" sch 160 and we are equipped with setting up to wrap each joint with controlled electric resistance or induction heating methods with monitoring from the start of welding to finish why could we not go right into PWHT if we are not moving it. The WPS states to bring it down too 200F prior to PWHT but I think that is for the reason if you have large spools that you want to put into the frurnace and have to add stress to the spools to lift them.
I would agree that as long as we are not handling the piping or putting any stresses on it immediately after weld completion there is no reason to cool to 200 before PWHT
can some let me know there thoughts.
Thanks
I would agree that as long as we are not handling the piping or putting any stresses on it immediately after weld completion there is no reason to cool to 200 before PWHT
can some let me know there thoughts.
Thanks