Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

parameter a2 of Figure UW-13.2 Sketch (r) and (s)

Status
Not open for further replies.

Tridiartha

Mechanical
Apr 8, 2020
2
Hello,

I would like to seek advices regarding the physical intrepretation of variable a2, as shown in ASME VIII Div 1, Figure UW-13.2 Sketch (r) and (s).

In those sketches, variable a2 is related with a construction line (with minimum 45 degree angle).

What is the purpose of this construction line?

Where could i find in the code, a relation between parameter a2 and ts?

I appreciate for any advices related with this matter.

Thank you.

Tridiartha







 
Replies continue below

Recommended for you

Tridiartha, first you need to thoroughly understand UW-13(e) and (f) rules for corner joints with flat heads, tubehseets, etc. UW-13(f) and sketches (r) & (s) provide alternate rules to UW-13(e) and related sketches and can produce a joint with perhaps less preparation and deposited weld than UW-13(e) joints.

You need to understand that use of UW-13(f) requires some knowledge of the ratio between the tensile strength in the in-plane and through thickness (Z) directions of the flat member of the joint (the K value). The less difference between the two, the less joint prep needed.

The detailed requirements are too complicated to go into just now, but to briefly answer your questions:

1) "What is the purpose of this construction line?" - The purpose is to more or less establish the weld penetration beyond the bevel (if any) required based on the assumed or known ratio between the tensile strengths, the K value.

2) "Where could i find in the code, a relation between parameter a2 and ts?" - It is found in the detailed requirements of UW-13(f), understanding that ts is first determined under the other relevant Code rules. a2 is then determined based on the details of the weld joint and other UW-13(f) rules.

Again I say, you need to first thoroughly understand UW-13(e) and (f) rules.

Regards,

Mike

The problem with sloppy work is that the supply FAR EXCEEDS the demand
 
Hi Mike,

Thank you for the advice.

I have made a sketch to refine my question. Please refer to the attached sketch.

Is it correct to intrepret that point A (on that sketch) was the starting point of construction line?

Regards,
Tridiartha
 
 https://files.engineering.com/getfile.aspx?folder=6a13fae8-3990-4f15-8079-97d712a515dd&file=Figure_UW-13.2_Sketch_(s).PNG
Tridiartha, yes that looks right to me.

The problem with sloppy work is that the supply FAR EXCEEDS the demand
 
Do you believe that all the conditions stated in UW-13 (f) can be met during manufacturing and inspection?
Did you read SA-770?
Do you understand the K factor?
I suggest that you consult a welding engineer and a manufacturer.
I also suggest that you change the design.

Regards
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor