qaqceng
Materials
- Jan 31, 2012
- 20
Hi,
We have a pair of ASME Section I drums being manufactured by a sub-contractor, whose workers have gone on strike indefinitely. The drums are in the middle of fabrication, and we are considering moving them to a new sub-contractor.
Both sub-contractors are ASME Stamp Holders. The drums have nozzle attachments that have CJP welds, welded from both sides. Prior to the worker strike, the current sub welded all of the nozzles from one side but not the other.
Could a new manufacturer take on responsibility for this work, and complete the nozzle welds from the other side? I understand they would need to stamp the parts and provide partial data reports, but it is an unusual circumstance to have welds that are only partially completed.
Thanks,
qaqceng
We have a pair of ASME Section I drums being manufactured by a sub-contractor, whose workers have gone on strike indefinitely. The drums are in the middle of fabrication, and we are considering moving them to a new sub-contractor.
Both sub-contractors are ASME Stamp Holders. The drums have nozzle attachments that have CJP welds, welded from both sides. Prior to the worker strike, the current sub welded all of the nozzles from one side but not the other.
Could a new manufacturer take on responsibility for this work, and complete the nozzle welds from the other side? I understand they would need to stamp the parts and provide partial data reports, but it is an unusual circumstance to have welds that are only partially completed.
Thanks,
qaqceng