Geotechnical Circular # 4 Appendix B lists the Wang-Reese equations for evaluating ultimate passive resistance for embedded beams.
See attached.
Does anyone have any references to a case where a caisson is drilled into the passive zone wedge (as in a drill hole next to a soldier pile)? Is there a critical distance between the soldier pile and the drilled caisson where the drilled hole collapses? What failure modes are introduced and how do you calculate the ultimate passive resistance?
Looked into casing and pre-drilling the caisson holes before excavation, but wanted to know if I could avoid this. Also realize that I can brace the bottom of the pile and not count on passive pressure....except I think it's impossible for cantilevered soldier piles.
See attached.
Does anyone have any references to a case where a caisson is drilled into the passive zone wedge (as in a drill hole next to a soldier pile)? Is there a critical distance between the soldier pile and the drilled caisson where the drilled hole collapses? What failure modes are introduced and how do you calculate the ultimate passive resistance?
Looked into casing and pre-drilling the caisson holes before excavation, but wanted to know if I could avoid this. Also realize that I can brace the bottom of the pile and not count on passive pressure....except I think it's impossible for cantilevered soldier piles.