Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

PE Stamp required on ASME Sect VIII, Div I vessels

Status
Not open for further replies.

waskillywabbit

Mechanical
Feb 26, 2004
302
A discussion between a friend and myself has my curiosity peeked. I don't see any such requirement in my ASME code books, that a PE stamp the drawings/desgin for fabrication...or is this more of a state law issue?

What is required to design and fabricate a pressure vessel...according to the law and the ASME code?

Your insight is appreciated.

Brian

Opinions expressed are my own and are not those of the company.
 
Replies continue below

Recommended for you

Per ASME it's not required for Div 1 but is required for Div. 2
 
weldtek,

Thank you, that is what I had thought, but needed some confirmation to convince my friend.

Brian
 
waskillywabbit (Mechanical) and Team Member's:

Division 2, page 15

ARTICLE G-3 RESPONSIBILITIES AND DUTIES

AG-301 USER’S RESPONSIBILITY

AG-301.2 Certification of User’s Design Specification.
A Professional Engineer, registered in one or
more of the states of the United States of America or
the provinces of Canada and experienced in pressure
vessel design, shall certify to the compliance of the
User’s Design Specifications with the above requirements.

lst
 
Note that if the work constitutes "engineering" as defined by state law, and is not exempt for some reason, then design by a PE (and corresponding PE seal) would be required regardless of what the code actually read. However, one of the exemptions is usually manufactured items, and many pressure vessels (for example, mass-produced air compressor tanks) would fall under that exemption.

In many, perhaps most, states, the PE seal requires that the work be done by, or under the direct supervision of, the PE in question, not merely reviewed and stamped after the fact.

Generally, for a custom-made vessel, the PE seal would be the state where it was to be installed, not the state of manufacture.

Check your state PE rules for the final answer. They're usually available online, among other places.
 
Brian-

As already pointed out, a VIII Div. 1 vessel has no ASME requirements for any PE stamps. Even in (at least some)states where the PE Act requires that all calc's be stamped this requirement is routinely ignored. I don't recall ever seeing a PE stamp on any documentation relating to a Div. 1 vessel. Perhaps on some consultant's report where the consultant felt like putting his stamp on the cover sheet.

Division 2, on the other hand requires not one but two PE stamps. These PE certifications could conceivably be the same but in practice are usually not. As Mr. Thill pointed out in his post, AG-301 requires that the user clearly detail the design requirements for the vessel (including things like design liquid level mentioned in another currently active post). This User's Design Specification must be certified by a PE.

The second PE stamp is required on the Manufacturer's Design Report which involves the calc's and design of the vessel to the design requirements called out in the User's Design Spec.

jt
 
Thanks for the responses guys. Does this mean I have to split the bet money 5 ways? :)

Brian
 
Brian-

Nah. Just buy us lunch and we'll call it even!

jt
 
waskillywabbit (Mechanical), jte where is the lunch being held? At the local PRESSURE VESSEL MEETING nest Wednesday in Houston?

Leonard Stephen Thill
 
Where is the Pressure Vessel Meeting Nest in Houston?
 
Sec VIII 1: even where the dwgs are stamped by a PE,
the mfr is responsible for the correctness, so
do not get fouled by a stamp.
ER
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor